Summary of Projects for 2006-2007
2006 Projects
- Taxiway lanes and ramp lines painted.
- Completion of the Auburn Flyer Condo III project at the South
end.
- Repaired and installed new SE exit gate for open hangar tenant
use.
- All AN-2 aircraft have been removed.
- Consultants were hired to evaluate and plan repairs for hangar
rows9 and 10 roofs.
- Started final
construction phase of remaining property at the North end of
airport to be completed in January of 2007
- Segmented circle painted with high visability paint.
- Two
meetings were held with FAA official and local pilots to evaluate
and consider options for possible changes to traffic patterns
used by rotorcraft. Results set to available in early 2007.
- A
Master Busines Planning Committee was formed and completed .
The objectives of the committee was to prepare, present and implement
master business plan for growth and development of the Auburn
Airport to the Mayor and Auburn City Council for approval.
- Landscaping
projects completed and in progress .
- West-side access road began construction.
- Runway repairs completed; damage caused by multiple prop strikes.
2007 Project Ideas and Plans
- Plans for the taxiway improvements and construction beginning
in 2008
- FAA publication
of GPS approach plate scheduled for May 2007.
- Repairs to hangars Rows 9 and 10.
- Airport signage repairs and replacement.
- Web page updates.
- garbage and recycling program underway.
|
|